Wrench Time
Home/Technician time/Waiting: the category nobody plans for

Technician time

Waiting: the category nobody plans for

Waiting for a part, a key, an isolation or a room is the least visible category of lost time and often the easiest to reduce.

7 min read522 wordsUpdated July 2026

Of the ways a maintenance hour is lost, waiting is the most frustrating and the least recorded. A technician standing outside a locked plant room is not idle by choice and is not doing maintenance, and in most systems that quarter of an hour is simply part of the job duration. For a separate product-side perspective on coordination between people during handoffs, this background note provides additional detail.

The four things people wait for

Parts. Either not in stock, or recorded as in stock and not actually there. The second is worse than the first, because the trip was made on the basis of the record.

Access. A locked room with no known key holder, an occupied space, a tenant area requiring notice, a client who has to be present. For a wider operational and compliance reference, consult OSHA hazard prevention guidance.

Isolation and permits. A system that cannot be worked on until someone authorises it, and the authoriser is in a meeting.

A second person. Two-person tasks — confined space, high level work, heavy lifts, live testing — where one technician arrives and the other is elsewhere.

Waiting is almost always someone else's process

Every category above is caused by a system outside the maintenance visit: stores accuracy, key management, permit authorisation, scheduling. Which is why it responds well to being fixed and not at all to being complained about.

Stores accuracy is the highest-value fix

A stores record that overstates what is present causes the worst version of the problem: a journey made, a job started, and a stop partway through. It also destroys trust in the system, after which technicians hoard parts privately, which makes the record less accurate still.

The fix is unglamorous — a cycle count on the highest-turnover items, issue recorded at the point of taking, and a bin location that matches the record. It typically takes a few weeks of discipline and removes a recurring loss for years.

Kit the planned work

Planned jobs are known in advance, which means the parts can be picked and staged before the technician starts. This converts a per-job trip to stores into one picking round done by one person.

It requires the planned task to specify its materials, which many inherited schedules do not. Adding a materials list to the twenty or thirty most frequent planned tasks is a bounded piece of work with an immediate and repeated return.

Access constraints belong on the asset

The information that a plant room key lives with a particular department, or that a tenant area needs a day's notice, is usually known by whoever has been there before and recorded nowhere.

Attaching it to the asset record means it appears on every future job automatically, including for a technician who has never attended that location and for the contractor who attends next year.

Record it, even roughly

A single waiting field on the job — even just a duration and a reason from a short list — turns an invisible loss into a countable one within a couple of months.

The output is usually a small number of specific causes concentrated in a small number of places: one plant room, one stores category, one permit authoriser who is unavailable. Each is fixable individually, and none of them would have been identified from an aggregate wrench-time figure alone.

General information, not legal or safety advice. Statutory inspection requirements, competence rules and working time law differ substantially between jurisdictions and change over time. Confirm the position that applies to you, and take competent advice, before acting on anything here.